The most expensive words in standby power: it started fine last month. Starting proves the battery, starter and fuel line, not that the set will carry your load.

Get servicing quotes

What a load bank test does

A load bank applies an artificial electrical load to the generator. It can then run up towards its rating without the real building load or an outage.

That exercises the engine and alternator properly and brings the engine to full operating temperature. It reveals faults a twenty minute off-load run never will:

  • cooling capacity
  • fuelling under load
  • exhaust and turbo condition
  • alternator regulation
  • the point at which something trips

Why lightly loaded standby sets need it

  • Light loading is bad for diesel engines. Running a set repeatedly at a small fraction of its rating leads to incomplete combustion and unburnt fuel and oil accumulating in the exhaust system, commonly called wet stacking. A properly loaded run is the standard remedy.
  • The building load is often not representative. Testing on the real load only proves the set can carry the load that happened to be running that day.
  • Faults hide at low load. Cooling, fuelling and governing problems appear as the engine approaches its rating, not while it idles.
  • It is the only honest evidence. A dated load test report with readings is what you want on file when the set has to work for real.

What to specify when you ask for a quote

  1. The load profile: what percentage of rating, in what steps, and for how long at each step.
  2. Who supplies the load bank, how it gets to the set, and what cabling and connection work is needed.
  3. Whether the building load is used first, with the load bank topping up to rating, which is often the cheaper and more realistic approach.
  4. What is recorded: voltages, currents, frequency, temperatures, pressures and fuel consumption against time, not a pass or fail line.
  5. What happens if it fails, because a load test that finds a fault is a success, and you want the repair quoting process agreed in advance.

How often

There is no statutory interval for load bank testing, as there is none for generator servicing generally. Frequency is set by the manufacturer's guidance, what the set protects, and your maintenance risk assessment. Sets carrying critical or life safety loads, and sets that rarely see real load, are where more frequent proving is easiest to justify.

If your set is large enough to fall inside the medium combustion plant or specified generator permitting regimes in England and Wales, testing regimes can interact with emissions obligations. Check whether your plant is in scope on gov.uk before planning a testing programme.

Get generator servicing quotes

Two minutes of questions; generator service providers covering your site quote you directly. Free, no obligation.

Your set

Roughly what size is the set?

  • Free, no obligation
  • Your details go to at most three providers
  • Takes about two minutes

Get a price for your actual set.

Two minutes of questions; generator service providers covering your site quote you directly. Free, no obligation.

Questions, answered directly

What is a generator load bank test?

A test that applies an artificial electrical load so the generator can run towards its rated output without the real building load or a power cut. It proves cooling, fuelling, alternator regulation and exhaust condition under genuine load, with a report of readings against time. It is bought separately from a routine engine service.

What is diesel generator load bank testing for?

To prove a diesel set can carry real load and to clear the effects of light running. Standby diesels run off-load or lightly loaded build up unburnt fuel and oil in the exhaust. A loadbank test runs the engine towards its rating, so it reaches full temperature, burns that off and shows a cooling, fuelling or alternator fault.

How often should a standby generator be load tested?

There is no statutory interval. Frequency comes from the manufacturer's guidance, the criticality of the load and your own risk assessment. Regular load testing is easiest to justify, and hardest to defend skipping, on sets that rarely run under real load and sets protecting critical or life safety systems.

What is wet stacking?

The build-up of unburnt fuel and oil in a diesel engine's exhaust when it is repeatedly run at too low a load to reach operating temperature. It is a known consequence of exercising standby sets off-load or on trivial loads. Running the engine properly loaded, on a load bank, is the standard way to prevent and clear it.

Sources

This site's own datasets, every figure quoted from its source and dated:

  • The median published figure in the UK Generator Service Price Index is 265 GBP across 3 sources' own pages (range 250 to 275 GBP), read 11 November 2026.
  • The UK Standby Generator Obligations carries 8 published figures read from 3 sources' own pages; the 3 published figures given without a breakdown run from 50 to 50 hour, read 7 November 2026.
  1. HSE. Provision and Use of Work Equipment Regulations 1998 (PUWER)
  2. HSE. PUWER overview
  3. HSE. Inspection of work equipment
  4. HSE. Maintenance of work equipment
  5. legislation.gov.uk. The Provision and Use of Work Equipment Regulations 1998
  6. gov.uk. Medium combustion plant and specified generators: environmental permits
Get servicing quotes